Requirement Gathering & Understanding

  • Requirement freezing
  • Android and iOS users
  • A number of admins & number of app users from total users
  • Report formats
  • QR code integration or simple checklist
  • Other features
  • Internal team discussion
  • Decide timeline of the project (must include timeline given by the developers)
  • Calls and mail/message communication with the client

Business Modeling

  • Hierarchy
  • Data access permission
  • Form access permission
  • Decide what features will be used in-app

Solution Document Creation

Forms Creation by SolDev

  • Form creation
  • Icon setting (Icon Folder Link: Icons)
  • Behavior mapping if scheduling is included

Forms UAT

  • Form UAT by the client for 2-3 days to experience the form and to collect their suggestions for the same
  • Make the changes suggested by the client. Email it to the client with proper screenshots and explanation of same in detail
  • After the client, confirmation freeze the checklist

Reports Creation by SolDev

  • Email, document, or excel templates

Reports UAT

  • Report format confirmation by the client on email by sending sample report to them and collect their suggestions for the same
  • Make the changes suggested by the client. Email it to the client with proper screenshots and an explanation of the same in detail
  • After the client, confirmation freeze the Report format

Workflows Creation

  • Create a workflow with proper approval & decision steps of Workflow builder and then test all workflows with the Forms & Reports and email templates

Integration (If required)

Platform Customization Tasks (If required)

Testing (30% time of total Solution Building time)

  • Testing (Update the testing status in the sheet)
  • Bug fixing (If any)
  • Re-testing and update the status to the developers or QA (Link to the Status Sheet: Status Sheet)

Client Training by Solution Developer

  • Demo of final app & train client on “How to use the solution
  • Note: (Record this session & send it to the client while delivering the application for better understanding)

UAT App Delivery Process

  • Data Import/ Data Added
  • Create users & edit passwords
  • Complete go-live checklist (Instruction set for app delivery)
  • Add users
  • Access permission & form permission
  • Update WF

UAT Start and End

  • UAT (7 to 15 days), Decide UAT based on the below factors:
    • Complexity of Project
    • Phase wise UAT

Dashboard (If required)

  • Wireframe creation (SolDev)
  • Approval from Developers
  • Approval from Client
  • Creation of Dashboard (Developers)
  • Testing of Dashboard (Developers & Solution Developer)

Dashboard Demo

  • Dashboard Demo to the client

Changes After UAT

  • Changes are done email to the client with proper screenshots and explanation of same in detail

Final app delivery process

  • Email
  • Known Issues/ release nos
  • Notes
  • Link of the university website
  • Credentials file
  • QR code (if any)
  • Steps to get started
  • Link to the play store or app store

Support

  • Service Call (Weekly) & Support client when required

Was This Article Helpful?